Jefferson Interchange Notice of Work, 3/1/16 – 3/3/16

Lane closures will take place on I-10 at Jefferson Street March 1 - 3. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Night of Tuesday to Thursday, March 1 - 3, 2016.
Time: 10:00 PM - 6:00 AM

Closures:

Alternating lane closures EB I-10 Freeway

Jefferson Interchange Notice of Work, 2/29/16 – 3/4/16

Ramp closures will take place on I-10 at Jefferson Street February 29 - March 4. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

Date: Monday to Friday. February 29 - March 4, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

Jefferson Interchange Update

The realigned I-10 WB on-ramp was opened on Friday afternoon. This realignment provides an extended auxiliary lane to facilitate smooth merges onto the I-10 freeway.

Traffic speed limits in both directions have been reduced on the I-10 through the Jefferson St. construction zone to 55 mph.  CHP will be enforcing this speed limit at all times until the completion of the project.

Jefferson Interchange Notice of Work, 2/22/16 – 2/26/16

Ramp closures will take place on I-10 at Jefferson Street February 22 - 26. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

Date: Wednesday to Friday. February 17 - 19, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Jefferson Interchange Notice of Work, 2/17/16 – 2/19/16

Ramp closures will take place on I-10 at Jefferson Street February 17 - 19. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Wednesday to Friday. February 17 - 19, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

 

Night closures will take place on WB I-10 at Jefferson Street February 17 - 19. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Full closure of WB I-10 on-ramp:

Thursday, February 18 6:00am to Friday, February 19, 2016 6:00am

Alternate 1

Closure of 2 and 3 lanes on WB I-10.

Wednesday through Friday, February 17 - 19, 2016 10:00pm - 6:00am

Alternate 2

Full closure of WB I-10.

Thursday through Friday, February 18 - 19, 2016 10:00pm - 6:00am

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Continue to Washington St. on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 2/8/16 – 2/11/16

Ramp closures will take place on I-10 at Jefferson Street February 8 - 11. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Monday to Thursday. February 8 - 11 2016

Time: 6:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp and off-ramp.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

This work has been cancelled for this week:

Night closures will take place on WB I-10 at Jefferson Street February 8 - 11. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Closure of 2 and 3 lanes on WB I-10: Monday through Wednesday, February 8 - 10, 2016 10:00pm - 6:00am

Full closure of WB I-10 on-ramp: Monday through Thursday, February 8 - 11, 2016 9:00pm - 7:00am

Full closure of WB I-10: Thursday, February 11, 2016 10pm - 6:00am

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Continue to Washington St. on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 2/4/16

Lane closures will take place on I-10 at Jefferson Street February 4. The purpose of this closure is to allow construction crews to place concrete pavement on the new EB on ramp.

Closure Schedule

Date: Night of Thursday, February 4, 2016.
Time: 10:00 PM - 6:00 AM

Closures:

Closure of 2 and 3 lanes on EB 1-10.

Jefferson Interchange Notice of Work, 2/1/16 – 2/5/16

Ramp closures will take place on I-10 at Jefferson Street February 1 - 5. The purpose of these closures is to allow the removal of bridge form panels.

Closure Schedule

Date: Monday to Friday. February 1 - 5, 2016

Time: 6:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp

Jefferson Interchange Notice of Work, 1/25/16 – 1/29/16

Ramp closures will take place on I-10 at Jefferson Street January 25 - 29. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Monday to Friday. January 25 - 29, 2016

Time: 5:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp and off-ramp at Jefferson St. and full closure of WB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue on Varner Rd. to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 1/18/16 – 1/22/16

Ramp closures will take place on I-10 at Jefferson Street January 18 - 22. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Monday to Friday. January 18 - 22, 2016

Time: 6:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp and off-ramp at Jefferson St. and full closure of WB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue on Varner Rd. to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 1/11/16 – 1/15/16

Ramp closures will take place on I-10 at Jefferson Street January 11 - 15. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Monday to Friday. January 11 - 15, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St. and full closure of WB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue on Varner Rd. to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 1/9/16

Ramp closures will take place on I-10 at Jefferson Street January 9. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Saturday. January 9, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St. and full closure of WB on-ramp at Jefferson St.

Note: Due to inclement weather this week, the Contractor is forced to work this Saturday to maintain the project schedule.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue on Varner Rd. to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 1/6/16 – 1/8/16

Ramp closures will take place on I-10 at Jefferson Street January 6 - 8. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Wednesday to Friday. January 6 - 8, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St. and full closure of WB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue on Varner Rd. to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 12/9/15

Lane closures will take place on I-10 at Jefferson Street December 9. The purpose of these closures is to place concrete pavement on the new EB auxiliary lane and off ramp.

Closure Schedule

Date: Wednesday night. December 9, 2015
Time: 8:00 PM - 6:00 AM

Closures:

Alternating lane closures of EB I-10. Closure of EB off-ramp at Jefferson St.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 12/7/15 – 12/11/2015

All full closures have been cancelled for this week.

Lane closures will take place on I-10 at Jefferson Street December 7 - 11.The purpose of these closures is to allow construction crews to place forms and reinforcement for bridge construction over the EB and WB I-10.

Closure Schedule

Date: Nights of Monday to Friday, December 7 - 22, 2015 CANCELLED
Time: 10:00 PM - 6:00 AM CANCELLED
Closures:

Alternate 1: Full closure of EB I-10. Closure of 1 and 2 lanes on WB 1-10.

Alternate 2: Full closure of WB I-10. Closure of 1 and 2 lanes on EB I-10.

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for full closure of EB I-10 at Jefferson Street Interchange

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing.
  3. Right on EB I-10 on-ramp at Jefferson St.

Notes:

Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on existing Jefferson over-crossing.
  4. Right on WB I-10 on-ramp.

Notes:

Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 12/7/15

Full closure of WB I-10 and WB on-ramp at Jefferson Street will take place on December 7. The purpose of these closures is to allow construction crews to construct an auxiliary lane at the WB on-ramp.

Closure Schedule

Date: Monday night. December 7, 2015
Time: 10:00 PM - 6:00 AM

Closures:

Full closure of WB I-10. Closure of WB on-ramp at Jefferson St.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on WB on-ramp at Washington St.

Notes: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 12/9/15

Full closure of WB I-10 and WB on-ramp at Jefferson Street will take place on December 9. The purpose of these closures is to allow construction crews to construct an auxiliary lane at the WB on-ramp.

Closure Schedule

Date: Monday night. December 9, 2015
Time: 10:00 PM - 6:00 AM

Closures:

Full closure of WB I-10. Closure of WB on-ramp at Jefferson St.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on WB on-ramp at Washington St.

Notes: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 11/30/15 – 12/4/15

**Update**  Closures for Monday through Wednesday have been cancelled.

Ramp closures will take place on I-10 at Jefferson Street November 30 - December 4. The purpose of these closures is to allow bridge construction work to continue.

Closure Schedule

Date: Monday to Friday. November 30 - December 4, 2015
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

Lane closures will take place on I-10 at Jefferson Street November 30 - December 4.The purpose of these closures is to allow construction crews to place forms and reinforcement for bridge construction over the EB and WB I-10.

Closure Schedule

Date: Nights of Monday to Friday, November 30 - December 4, 2015
Time: 10:00 PM - 6:00 AM
Closures:

Alternate 1: Full closure of EB I-10. Closure of 1 and 2 lanes on WB 1-10.

Alternate 2: Full closure of WB I-10. Closure of 1 and 2 lanes on EB I-10.

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for full closure of EB I-10 at Jefferson Street Interchange

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing.
  3. Right on EB I-10 on-ramp at Jefferson St.

Notes:

Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on existing Jefferson over-crossing.
  4. Right on WB I-10 on-ramp.

Notes:

Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 11/23/15 – 11/24/15

Ramp closures will take place on I-10 at Jefferson Street November 23 - 24 The purpose of these closures is to allow bridge construction work to continue.

Closure Schedule

Date: Monday to Friday. November 23 - 24, 2015
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.


Lane closures will take place on I-10 at Jefferson Street November 23 - 24.The purpose of these closures is to allow construction crews to place forms and reinforcement for bridge construction over the EB and WB I-10.

Closure Schedule

Date: Nights of Monday to Tuesday. November 23 - 24, 2015
Time: 10:00 PM - 6:00 AM
Closures:

Alternate 1: Full closure of EB I-10. Closure of 1 and 2 lanes on WB 1-10.

Alternate 2: Full closure of WB I-10. Closure of 1 and 2 lanes on EB I-10.

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Detour for full closure of EB I-10 at Jefferson Street Interchange

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing.
  3. Right on EB I-10 on-ramp at Jefferson St.

Notes:

Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on existing Jefferson over-crossing.
  4. Right on WB I-10 on-ramp.

Notes:

Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 11/16/15 – 11/20/15 (CANCELLED)

** All off-ramp closures and on-ramp closures for Monday and Tuesday have been canceled **

Ramp closures will take place on I-10 at Jefferson Street November 16 - 20 The purpose of these closures is to allow bridge construction work to continue.

Closure Schedule

Date: Monday to Friday. November 16 - 20, 2015
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

**Freeway closures have been canceled.**

Lane closures will take place on I-10 at Jefferson Street November 16 - 20.The purpose of these closures is to allow construction crews to place forms and reinforcement for bridge construction over the EB and WB I-10.

Closure Schedule

Date: Nights of Monday to Friday. November 16 - 20, 2015
Time: 10:00 PM - 6:00 AM
Closures:

Alternate 1: Full closure of EB I-10. Closure of 1 and 2 lanes on WB 1-10.

Alternate 2: Full closure of WB I-10. Closure of 1 and 2 lanes on EB I-10.

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Detour for full closure of EB I-10 at Jefferson Street Interchange

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing.
  3. Right on EB I-10 on-ramp at Jefferson St.

Notes:

Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on existing Jefferson over-crossing.
  4. Right on WB I-10 on-ramp.

Notes:

Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 11/9/15, 11/12/15, 11/13/15

Ramp closures will take place on I-10 at Jefferson Street November 9, 12, and 13. The purpose of this closure is to allow bridge construction work to continue.

Closure Schedule

Date: Monday, Thursday, Friday. November 9, 12, 13, 2015
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.


Lane closures will take place on I-10 at Jefferson Street November 9, 12, and 13.The purpose of this closure is to allow construction crews to place forms and reinforcement for bridge construction over the EB and WB I-10.

Closure Schedule

Date: Nights of Monday, Thursday, Friday. November 9, 12, 13, 2015
Time: 10:00 PM - 6:00 AM
Closures:

Alternate 1: Full closure of EB I-10. Closure of 1 and 2 lanes on WB 1-10.

Alternate 2: Full closure of WB I-10. Closure of 1 and 2 lanes on EB I-10.

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Detour for full closure of EB I-10 at Jefferson Street Interchange

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing.
  3. Right on EB I-10 on-ramp at Jefferson St.

Notes:

Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on existing Jefferson over-crossing.
  4. Right on WB I-10 on-ramp.

Notes:

Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 11/2/15 – 11/6/15

Ramp closures will take place on I-10 at Jefferson Street November 2 - 6. The purpose of this closure is to allow bridge construction work to continue.

Closure Schedule

Date: Monday to Friday. November 2 - 6, 2015
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp and off-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Lane closures will take place on I-10 at Jefferson Street November 2 - 6.The purpose of this closure is to allow construction crews to place forms and reinforcement for bridge construction over the EB and WB I-10.

Closure Schedule

Date: Nights of Monday to Friday. November 2 - 6, 2015
Time: 10:00 PM - 6:00 AM
Closures:

Alternate 1: Full closure of EB I-10. Closure of 1 and 2 lanes on WB 1-10.

Alternate 2: Full closure of WB I-10. Closure of 1 and 2 lanes on EB I-10.

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Detour for full closure of EB I-10 at Jefferson Street Interchange

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing.
  3. Right on EB I-10 on-ramp at Jefferson St.

Notes:

Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10 at Jefferson Street Interchange

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on existing Jefferson over-crossing.
  4. Right on WB I-10 on-ramp.

Notes:

Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work – July 6, 2015

Nighttime work and lane closures on I-10 at Jefferson Street Interchange

Beginning July 6th, construction crews will be performing nighttime work and lane closures on I-10 at the Jefferson Street Interchange. This work will last through July 14th. The purpose of this work is to place k-rail, re-stripe I-10 and shift traffic.

CLOSURE SCHEDULE

Nights of July 6 and July 7 (10:00 PM – 6:00 AM)

  • Re­-stripe I­-10 in both directions and shift traffic towards median.

Nights of July 8 and July 9 (10:00 PM – 6:00 AM)

  • Place K-­rail on westbound side of I­-10

Nights of July 13 and July 14 (10:00 PM – 6:00 AM)

  • Place K-­rail on eastbound side of I­-10

DETOURS

No detours are necessary for these closures. At least one lane will be open in each direction at all times.

Notice of Work – April 20, 21, 22

On the nights of April 20, 21 and 22, the I-10 / Jefferson Street Interchange Project contractor will be hauling excavated material out of the I-10 median and delivering pile driving material and equipment into the construction zone. This work will require the closure of the number 1 and 2 lanes on EB I-10 at Jefferson Street.

The closures will take place all three nights between the hours of 10:00 PM and 6:00 AM.

No detour is required for these closures.

Notice of Work – April 7, 2015

I-10 / Jefferson Street Interchange Project

The I-10 / Jefferson Street Interchange Project contractor will perform lane closures on I-10 at Jefferson Street the night of Tuesday, April 7th between 10:00 pm and 6:00 am

The alternating closures will take place on the number 1 and number 2 lanes on EB and WB I-10. The purpose of these lane closures is to allow the contractor to:

  • Install k-rail in the median
  • Install storm water pollution preventention measures
  • Install fencing to identify environmentally sensitive areas
  • Begin excavating, install shoring and drive piles within the median

The contractor's operations have been planned to minimize impacts to motorists traveling to and from the Coachella Valley Music and Arts Festival and Stagecoach. K-rail will be installed in order to provide a safety barrier for workers and the traveling motorists. All existing lanes along I-10 in the construction area will be available to motorists after the k-rail has been installed.
Click here to view the Notice of Work

www.i10cvcprojects.com

Questions? Please call Dennis Green at (909) 800-0451.