Jefferson Interchange Notice of Work, 1/25/16 – 1/29/16

Ramp closures will take place on I-10 at Jefferson Street January 25 - 29. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Monday to Friday. January 25 - 29, 2016

Time: 5:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp and off-ramp at Jefferson St. and full closure of WB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue on Varner Rd. to Washington St. on-ramp.