Jefferson Interchange Notice of Work, 2/17/16 – 2/19/16

Ramp closures will take place on I-10 at Jefferson Street February 17 - 19. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Wednesday to Friday. February 17 - 19, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

 

Night closures will take place on WB I-10 at Jefferson Street February 17 - 19. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Full closure of WB I-10 on-ramp:

Thursday, February 18 6:00am to Friday, February 19, 2016 6:00am

Alternate 1

Closure of 2 and 3 lanes on WB I-10.

Wednesday through Friday, February 17 - 19, 2016 10:00pm - 6:00am

Alternate 2

Full closure of WB I-10.

Thursday through Friday, February 18 - 19, 2016 10:00pm - 6:00am

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Continue to Washington St. on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue to Washington St. on-ramp.