Ramp closures will take place on I-10 at Jefferson Street May 16 - 20. The purpose of these closures is to continue bridge construction activities.
Closure Schedule
EB on-ramp day: Monday through Friday, May 16 - 20, 2016 6:00 AM - 4:00 PM
EB on-ramp night: Monday through Friday, May 16 - 20, 2016 7:00 PM - 9:00 AM
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour for closure of EB I-10 On-ramp at Jefferson St.
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
Turn left at the EB I-10 on-ramp.
Lane closures will take place on I-10 at Jefferson Street May 16 - 20. The purpose of these closures is to continue bridge construction activities.
Closure Schedule
Alternate 1
Night full closure of EB I-10. Closure of alternating lanes on WB 1-10.
Night of Monday Through Friday, May 16 - 20, 2016. 10:00pm - 6:00am
Alternate 2
Night full closure of WB I-10. Closure of alternating lanes on EB 1-10.
Night of Monday Through Friday, May 16 - 20, 2016. 10:00pm - 6:00am
Note: Only one alternative will be used each night.
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour for full closure of EB I-10.
- Take the EB I-10 off-ramp at Jefferson St.
- Left on existing Jefferson over-crossing
- Right on Varner Rd.
- Right on Monroe St.
- Left on EB I-10 on-ramp at Monroe St.
Note: Traffic will be flagged through the EB I-10 off-ramp.
Detour for full closure of WB I-10.
- Take the temporary WB I-10 off-ramp at Jefferson St.
- Left on Varner Rd.
- Left on Jefferson St.
- Right on Jefferson St. WB on-ramp
Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.