Jefferson Interchange Notice of Work, 5/22/17 – 5/25/17

Ramp closures will take place on I-10 at Jefferson Street May 22 - 25. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Thursday, May 22 - 25, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Nights of Wednesday and Thursday, May 24 - 25, 2017. 7:00 PM - 6:00 AM

EB off-ramp day:

Monday through Thursday, May 22 - 25, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.