Jefferson Interchange Notice of Work, 6/6/16 – 6/10/16

Ramp closures will take place on I-10 at Jefferson Street June 6 - 10. The purpose of these closures is to  continue bridge construction activities.

Closure Schedule

EB on-ramp day: Monday through Friday, June 6 - 10, 2016 6:00 AM - 4:00 PM

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street June 6 - 10. The purpose of these closures is to continue bridge construction activities.

Closure Schedule

Night closure of alternating lanes on EB I-10.

Night of Monday through Friday, June 6 - 10, 2016. 10:00pm - 6:00am

Night closure of alternating lanes on WB I-10.

Night of Monday through Friday, June 6 - 10, 2016. 10:00pm - 6:00am
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.