Jefferson Interchange Notice of Work, 8/21/17 – 8/25/17 (Updated)

Ramp closures will take place on I-10 at Jefferson Street August 21 - 25. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB off-ramp day:

Thursday and Friday, August 24 - 25, 2017. 5:00 AM - 5:00 PM

WB on-ramp day:

Monday through Friday, August 21 - 25, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street August 21 - 25. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

EB I-10 full closure night:

Monday through Friday, August 21 - 25, 2017. 10:00 PM - 6:00 AM

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Washington St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.

Turn left at Monroe St. on-ramp.