Jefferson Interchange Notice of Work, 9/6/16 – 9/9/16

Lane closures will take place on I-10 at Jefferson Street September 6 - 9. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night  alternating lane closures of EB I-10.

Nights of Tuesday through Friday, September 6 - 9, 2016. 10:00pm - 6:00am

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

 

Ramp closures will take place on I-10 at Jefferson Street September 7 - 9. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day: Wednesday through Friday, September 7 - 9, 2016 3:00 AM - 4:00 PM

EB off-ramp night: Wednesday through Friday, September 7 - 9, 2016 7:00 PM - 4:00 PM (21 hour closure)

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.