Jefferson Interchange Notice of Work – July 6, 2015

Nighttime work and lane closures on I-10 at Jefferson Street Interchange

Beginning July 6th, construction crews will be performing nighttime work and lane closures on I-10 at the Jefferson Street Interchange. This work will last through July 14th. The purpose of this work is to place k-rail, re-stripe I-10 and shift traffic.

CLOSURE SCHEDULE

Nights of July 6 and July 7 (10:00 PM – 6:00 AM)

  • Re­-stripe I­-10 in both directions and shift traffic towards median.

Nights of July 8 and July 9 (10:00 PM – 6:00 AM)

  • Place K-­rail on westbound side of I­-10

Nights of July 13 and July 14 (10:00 PM – 6:00 AM)

  • Place K-­rail on eastbound side of I­-10

DETOURS

No detours are necessary for these closures. At least one lane will be open in each direction at all times.