Traffic Alert for North Indio Regional Flood Control Project

Traffic alert Avenue 38

Avenue 38 west of Jefferson Street will reopen to through traffic on April 1, 2024.

Traffic alert Jefferson Street

The temporary detour at Jefferson Street and Avenue 40 will be removed and permanently paved before reopening to through traffic on April 1, 2024.

Traffic alert Adams Street near Avenue 39

A section of Adams Street will close starting the first week of April through the end of July while crews construct a new reinforced concrete box culvert across Adams Street.

Adams Street detour plan

Northbound traffic: East on Avenue 40, north on Jefferson Street, west on Avenue 39.

Southbound traffic: East on Avenue 38 or Avenue 39, south on Jefferson Street, west on Avenue 40

Signs will redirect drivers around the closure.

See detour map here.

For more information on this project visit the North Indio Regional Flood Control Project webpage.

Coachella Valley Water District, PO Box 1058 Coachella, CA 92236
Phone (760) 398-2651 | Contact Us

CVWD Early Work Start Time Notice (February 17)

Coachella Valley Water District Storm Channel Project
Early Work Start Time Notice – February 17

On Friday, February 17, 2023, Sukut Construction will be pouring the walls on the Main Channel Outlet. The concrete pouring is currently scheduled to occur at 4:00am. The crew will be onsite between 3:00am – 3:30am to set up the concrete pump.

We thank you for your continued patience. For questions or information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401.

CVWD Early Work Start Time Notice (February 1)

Coachella Valley Water District Storm Channel Project
Early Work Start Time Notice – February 1

Sukut Construction will be pouring the slopes at Sun City Shadow Hills on Wednesday, February 1, 2023. The concrete is currently scheduled at 4:00am and the crew will be onsite between 3:00am – 3:30am to set up the concrete pump.

We thank you for your continued patience. For questions or information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401.

UPDATE: CVWD Early Work Start Time Notice

Coachella Valley Water District Storm Channel Project
Early Work Start Time Notice

Sukut Construction will be pouring slopes at Sun City Shadow Hills on Friday, January 13, 2023 *. The concrete pour is currently scheduled at 4:00am and the crew will be onsite between 3:00am – 3:30am to set up the concrete pump.

* Note: this slope pour was previously scheduled for Thursday, January 12, 2023.

 

We thank you for your continued patience. For questions or information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401.

CVWD Early Work Start Time Notices

Coachella Valley Water District Storm Channel Project
Early Work Start Time Notices

Sukut will be pouring the invert at Sun City Shadow Hills on Thursday, December 29, 2022. The concrete pour is scheduled at 4:00am and the crew will be onsite between 3:00am – 3:30am to set up the concrete pump.

Additionally, Sukut will have the grading crew starting at 5:00am from Tuesday, January 3, 2023, through Friday, January 13, 2023.

We thank you for your continued patience. For questions or information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401.

CVWD Early Work Start Time Notice (December 15)

Coachella Valley Water District Storm Channel Project
3:00 am Early Work Start Time Notice

What: Sukut Construction will be operating heavy equipment at the North Channel Construction Zone.

When: Thursday, December 15, 2022, 3:00 am – 2:30 pm

Construction Zone: The channel near the southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills.

What to expect: A bit of noise as equipment move around the area. Sukut Construction will be implementing all necessary actions to control dust and any associated air pollution within the project footprint by following applicable laws, rules, and regulations of the governmental entities having jurisdiction (City, State, etc.) as outlined in the contract documents.

We thank you for your patience on this project. For more information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401

CVWD Early Work Start Time Notice (October 31)

Coachella Valley Water District Storm Channel Project
6:00 am Early Work Start Time Notice

What: Sukut Construction will be pouring concrete at the North Channel at 7:00am. The crew will be onsite between 6:00am – 6:30am.

When: Monday, October 31, 2022, 6:00 am

Construction Zone: The channel near the Southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills.

What to expect: Moderate noise emitted from machinery. Sukut Construction will implement all necessary actions to control dust and any associated air pollution within the project footprint by following applicable laws, rules, and regulations of the governmental entities having jurisdiction (City, State, etc.) as outlined in the contract documents.

We thank you for your continued patience during this project. For more information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401.

CVWD Early Work Start Time Notice (October 26)

Coachella Valley Water District Storm Channel Project
3:00 am Early Work Start Time Notice

What: Sukut Construction will be operating heavy equipment at the North Channel Construction Zone.

When: Wednesday, October 26, 2022, 3:00 am – 2:30 pm

Construction Zone: The channel near the Southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills.

What to expect: Some noise as the equipment moves around the area. Sukut Construction will be implementing all necessary actions to control dust and any associated air pollution within the project footprint by following applicable laws, rules, and regulations of the governmental entities having jurisdiction (City, State, etc.) as outlined in the contract documents.

We thank you for your continued patience during this project. For more information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401.

CVWD Early Work Start Time Notice (July 20-22)


Coachella Valley Water District Storm Channel Project
4:00 am Early Work Start Time Notice

What: Sukut Construction will be operating heavy equipment at the North Channel Construction Zone.

When: Wednesday, July 20 – Friday, July 22, 4:00 am – 2:30 pm

Construction Zone: The channel near the southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills.

What to expect: A bit of noise as equipment move around the area. Sukut Construction will be implementing all necessary actions to control dust and any associated air pollution within the project footprint by following applicable laws, rules, and regulations of the governmental entities having jurisdiction (City, State, etc.) as outlined in the contract documents.

We thank you for your patience on this project. For more information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401

 

CVWD Early Work Start Time Notice (July 9)


Coachella Valley Water District Storm Channel Project
3:00 am Early Work Start Time Notice

What: Sukut Construction will be pouring concrete along the Channel walls inside the North Channel Construction Zone.

When: Saturday, July 9, 3:00 am – 2:30 pm

Construction Zone: The channel near the southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills. Same area as in late April, early May. Sukut Construction will be pouring concrete on the southern section half of the construction zone.

 

What to expect: A bit of noise as trucks move around the area. Depending on the weather and other factors, pours may last longer than 2:30 pm Crews will do their best to finish by 2:30 pm

We thank you for your patience on this project. For more information, please contact the SCSH Facilities Department at 760-345-4349 Ext. 2401

 

CVWD Early Work Start Time Notice (June 24)

3:00 AM Early Work Start Time Notice

What: Sukut Construction will be pouring concrete along the Channel walls inside the North Channel Construction Zone.

When: Friday, June 24, 3:00 am – 2:30 pm

Construction Zone: The channel near the southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills. Same area as in late April, early May. Sukut Construction will be pouring concrete on the southern section half of the construction zone.

What to expect: A bit of noise as trucks move around the area. Depending on the weather and other factors, pours may last longer than 2:30 pm Crews will do their best to finish by 2:30 pm

We thank you for your patience on this project. For more information, please contact the SCSH Facilities Department at 760-345-4349, ext. 2401.

CVWD Storm Channel Project Update: Dust Control

CVWD and Sukut Construction (Sukut) understand the concerns with dust caused by high winds in North Indio where the North Indio Flood Control Project – phase 2 (Project) is under construction. Sukut can control dust and any associated air pollution within the project footprint by following applicable laws, rules, and regulations of the governmental entities having jurisdiction (City, State, etc.) as outlined in the contract documents.

The Air Quality Management District has inspected the construction site on March 18, March 28, April 11, and May 26 and did not find any violations causing dust related to construction activity.

Many communities in the valley are surrounded by undeveloped desert including North Indio and are susceptible to dust and sand accumulation from the season’s unusual high winds.

Here are the actions being done to minimize dust from construction activities, which also meet contract requirements:

  • Watering dirt piles associated with construction.
  • Applying a soil binder to stockpiles of dirt.
  • Watering dirt on trucks before they leave for transportation.
  • Sweeping and vacuuming sand from the roads near constructions sites even if caused by wind from undeveloped land.

CVWD and its contractors will continue to minimize dust associated with construction activities but are not responsible for dust coming from undeveloped land. We thank everyone for their patience during this important project.

CVWD Project Website:
☞ https://www.cvwd.org/NorthIndio

Double Dump Trucks on Avenue 40

The CVWD North Basin project and the CVWD Avenue 40 storm drain projects are requiring a massive number of 18-wheel double-dump trucks to haul away the excavated dirt. The trucks use Avenue 40 both east and westbound and travel fully loaded at high speeds passing all Avenue 40 gate entrances, and the Shadows driveway entrance, and when crossing Jefferson Street. Please USE EXTREME CAUTION when entering the Avenue 40 roadway from any location to avoid a collision with one of these trucks. This will continue for several more weeks or months.

CVWD Early Work Start Time Notice

6:00 AM Early Work Start Time Notice

What: Sukut Construction will be pouring concrete along the channel walls inside the North Channel Construction Zone.

When: 6:00 am – 2:30 pm Friday, May 13; Monday, May 16; Tuesday, May 17; and Friday, May 20.

Construction Zone: The channel near the southeast corner of 40th Avenue and Jefferson Street. Near the old pond area in Sun City Shadow Hills. Same area as in late April, early May. Sukut Construction will be pouring concrete on the southern section half of the construction zone.

What to expect: A bit of noise as trucks move around the area. Depending on the weather and other factors, pours may last longer than 2:30 pm Crews will do their best to finish by 2:30 pm

We thank you for your patience on this project. For more information, please contact the SCSH Facilities Department at 760-345-4349 ext. 2401.

CVWD Early Work Start Time Notice

6:00 AM Early Work Start Time Notice

What: Sukut Construction will be pouring concrete along the channel walls inside the North Channel Construction Zone.

When: 6:00 AM – 2:30 PM, Friday, Monday, Tuesday (April 29, May 2, May 3)

Construction Zone: The channel near the southeast corner of 40th Avenue and Jefferson Street. Sukut Construction will be pouring concrete on the southern section half of the construction zone.

What to expect: A bit of noise as trucks move around the area. Depending on the weather and other factors, pours may last longer than 2:30 PM. Crews will do their best to finish by 2:30 PM.

For more information, please contact the SCSH Facilities Department, at 760-345-4349 ext. 2401.

CVWD Storm Channel Project Updates

Current CVWD Storm Channel Project Updates

  • Pond 1 had been drained and demolished.
  • All existing sidewalk in the construction zone has been demolished.
  • The reeds and pond liner has been removed.
  • The contractor, Sukut, is waiting for the soil to dry out presumably before they start the major excavation.

North Channel Pond 2 Conversion Project

  • Project will commence on March 7, with a completion time frame of 42 days.
  • Area will be fenced off from the south end of the Jefferson underpass entrance and along the pony-walls of the surrounding homes.
  • Landscape Unlimited will be delivering their equipment needed to drain and demolished the pond on Monday, March 7.
  • All wildlife such as turtles and fishes will be relocated to Pond 3.

North Indio Stormwater Flood Control Project Schedule Update

The CVWD construction contractor, Sukut Construction, has provided the following schedule for planned near-term work in our North Channel.

  • February 16
    • Cut an opening in our perimeter fence and install a gate with locks in order to create an access to the North Channel for construction equipment.
    • Begin installation of the temporary fence to surround the limits of the construction site.
  • February 17-18
    • Begin removing shrubs, trees, benches and concrete within the construction site.
  • February 22-25
    • Begin draining pond 1.
    • Capturing fish and turtles to be relocated to Lake 3, working side-by-side with a biologist.
  • February 24
    • Bring earthmoving equipment into the site and begin heavy excavation to accommodate construction of the concrete walls on either side of the pond that will protect the adjacent houses from future stormwater erosion. The location of the concrete walls is shown in the plan view below.

North Indio Regional Flood Control Project

As you may be aware, the North Indio Regional Flood Control Project has begun in surrounding areas and at the corner of Jefferson Street and Avenue 40. Please be advised that Sukut Construction will be on-site as early as next week to commence work in the North Channel Pond Area.

The work will include the installation of a fence to secure the construction site. The fence will be installed along the east side of the upper North Channel adjacent to the homes on Camino Montecito and across to our perimeter fence on Jefferson Street. The North Channel area will be closed to pedestrian traffic at the Sun City Blvd crossing for the duration of the construction. The first step in the construction will be to drain pond 1 and pond 2 to prepare the area for excavation and grading.

We thank you for your continued patience as we work alongside CVWD and Sukut Construction for a smooth project.

For your reference, please click on the link below for additional information.

https://www.cvwd.org/570/North-Indio-Regional-Flood-Control-Proje

Attachments:

πŸ“„ SCSH Construction and Lake Draining E_Blast_2022_02_11_FINAL.pdf

πŸ“„ SCSH Construction Zone Map.jpg

Second CVWD Storm Channel Project Town Hall Video Now Available

For all updates related to this project, please visit www.scshca.com/cvwd