Jefferson Interchange Notice of Work, 10/6/17 – 11/8/17

Ramp closures will take place on I-10 at Jefferson Street November 6 - 8. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday and Wednesday, November 6 and 8, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Nights of Monday through Wednesday, November 6 - 8, 2017. 7:00 PM - 5:00 AM

EB off-ramp day:

Monday and Wednesday, November 6 and 8, 2017, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Nights of Monday through Wednesday, November 6 - 8, 2017. 7:00 PM - 5:00 AM

WB off-ramp day:

Monday and Wednesday, November 6 and 8, 2017. 5:00 AM - 5:00 PM

WB off-ramp night:

Nights of Monday through Wednesday, November 6 - 8, 2017. 9:00 PM - 6:00 AM

WB on-ramp day:

Monday and Wednesday, November 6 and 8, 2017. 5:00 AM - 5:00 PM

WB on-ramp night:

Nights of Monday through Wednesday, November 6 - 8, 2017. 9:00 PM - 7:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right
  2. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street November 6 - 8. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night alternating lane closure of WB I-10.

Nights of Monday through Wednesday, November 6 - 8, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Monday through Wednesday, November 6 - 8, 2017. 10:00pm - 6:00am

Jefferson Interchange Notice of Work, 10/30/17 – 11/3/17

Ramp closures will take place on I-10 at Jefferson Street October 30 - November 3. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, October 30 - November 3, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Nights of Monday through Friday, October 30 - November 3, 2017. 7:00 PM - 5:00 AM

EB off-ramp day:

Monday through Friday, October 30 - November 3, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Nights of Monday through Friday, October 30 - November 3, 2017. 7:00 PM - 5:00 AM

WB off-ramp day:

Monday through Friday, October 30 - November 3 2017. 5:00 AM - 5:00 PM

WB off-ramp night:

Nights of Monday through Friday, October 30 - November 3, 2017. 9:00 PM - 6:00 AM

WB on-ramp day:

Monday through Friday, October 30 - November 3, 2017. 5:00 AM - 5:00 PM

WB on-ramp night:

Nights of Monday through Friday, October 30 - November 3, 2017. 9:00 PM - 7:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right
  2. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.
  2. Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street October 30 - November 3. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night alternating lane closure of WB I-10.

Nights of Monday through Friday, October 30 - November 3, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Monday through Friday, October 30 - November 3, 2017. 10:00pm - 6:00am

Jefferson Interchange Notice of Work, 10/23/17 – 10/27/17

Ramp closures will take place on I-10 at Jefferson Street October 23 - 27. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, October 23 - 27, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Nights of Monday through Friday, October 23 - 27, 2017. 7:00 PM - 5:00 AM

EB off-ramp day:

Monday through Friday, October 23 - 27, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Nights of Monday through Friday, October 23 - 27, 2017. 7:00 PM - 5:00 AM

WB off-ramp day:

Monday through Friday, October 23 - 27, 2017. 5:00 AM - 5:00 PM

WB off-ramp night:

Nights of Monday through Friday, October 23 - 27, 2017. 9:00 PM - 6:00 AM

WB on-ramp day:

Monday through Friday, October 23 - 27, 2017. 5:00 AM - 5:00 PM

WB on-ramp night:

Nights of Monday through Friday, October 23 - 27, 2017. 9:00 PM - 7:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right
  2. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street October 23 - 27. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night alternating lane closure of WB I-10.

Nights of Monday through Friday, October 23 - 27, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Monday through Friday, October 23 - 27, 2017. 10:00pm - 6:00am

Jefferson Interchange Notice of Work, 10/19/17 – 10/20/17

Street closures will take place on I-10 at Jefferson Street October 19 - 20. The purpose of these closures is to  resurface existing streets adjacent to the I10 / Jefferson St. Interchange project.

Closure Schedule

Full closure of Avenue 42 between Madison St. and Monroe St.

Thursday, October 19, 2017. 6:00 AM - 4:00 PM

Full closure of Jefferson St. between Varner Rd. and Indio Blvd.

Southbound Jefferson St.

Thursday and Friday, October 19 - 20, 2017. 6:00 AM - 4:00PM

Northbound Jefferson St.

Thursday and Friday, October 19 - 20, 2017. 9:00 AM - 4:00PM

Jefferson Interchange Notice of Work, 10/9/17 – 10/13/17

Ramp closures will take place on I-10 at Jefferson Street October 9 - 13. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, October 9 - 13, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Nights of Monday through Friday, October 9 - 13, 2017. 7:00 PM - 5:00 AM

EB off-ramp day:

Monday through Friday, October 9 - 13, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Nights of Monday through Friday, October 9 - 13, 2017. 7:00 PM - 5:00 AM

WB off-ramp day:

Monday through Friday, October 9 - 13, 2017. 5:00 AM - 5:00 PM

WB off-ramp night:

Nights of Monday through Friday, October 9 - 13, 2017. 9:00 PM - 6:00 AM

WB on-ramp day:

Monday through Friday, October 9 - 13, 2017. 5:00 AM - 5:00 PM

WB on-ramp night:

Nights of Monday through Friday, October 9 - 13, 2017. 9:00 PM - 7:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right
  2. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street October 9 - 13. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Alternate 1

Night full closure of EB I-10.

Nights of Monday through Friday, October 9 - 13, 2017. 10:00pm - 6:00am

Night alternating lane closure of WB I-10.

Nights of Monday through Friday, October 9 - 13, 2017. 10:00pm - 6:00am

Alternate 2

Night full closure of WB I-10.

Nights of Monday through Friday, October 9 - 13, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Monday through Friday, October 9 - 13, 2017. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Jefferson St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.
  4. Turn left at Monroe St. on-ramp.

Detour for full closure of WB I-10 at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave. 42.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 10/2/17 – 10/6/17

Lane closures will take place on I-10 at Jefferson Street October 2 - 6. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night alternating lane closure of WB I-10.

Nights of Wednesday  through Friday, October 2 - 6, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Wednesday  through Friday, October 2 - 6, 2017. 10:00pm - 6:00am

 

Ramp closures will take place on I-10 at Jefferson Street October 2 - 6. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, October 2 - 6, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Monday through Friday, October 2 - 6, 2017. 7:00 PM - 5:00 AM

EB off-ramp day:

Monday through Friday, October 2 - 6, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Monday through Friday, October 2 - 6, 2017. 7:00 PM - 5:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 9/25/17 – 9/29/17

Ramp closures will take place on I-10 at Jefferson Street September 25 - 29. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, September 25 - 29, 2017. 5:00 AM - 5:00 PM

WB loop on-ramp day:

Monday through Friday, September 25 - 29, 2017. 5:00 AM - 5:00 PM

WB on-ramp day:

Monday through Friday, September 25 - 29, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of WB I-10 Loop On-ramp at Jefferson St.

  1. Continue on Indio Blvd. north.
  2. Turn left at Varner Rd.
  3. Continue on Varner Rd. to Washington St. WB on-ramp.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

Jefferson Interchange Notice of Work, 9/18/17 – 9/22/17

Ramp closures will take place on I-10 at Jefferson Street September 18 - 22. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, September 18 - 22, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Monday through Friday, September 18 - 22, 2017. 7:00 PM - 5:00 AM

WB loop on-ramp night:

Monday through Friday, September 18 - 22, 2017. 9:00 PM - 7:00 AM

WB on-ramp night:

Monday through Friday, September 18 - 22, 2017. 9:00 PM - 7:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 Loop On-ramp at Jefferson St.

  1. Continue on Indio Blvd. north.
  2. Turn left at Varner Rd.
  3. Continue on Varner Rd. to Washington St. WB on-ramp.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street September 20 - 22. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Alternate 1

Night full closure of EB I-10.

Nights of Wednesday  through Friday, September 20 - 22, 2017. 10:00pm - 6:00am

Night alternating lane closure of WB I-10.

Nights of Wednesday  through Friday, September 20 - 22, 2017. 10:00pm - 6:00am

Alternate 2

Night full closure of WB I-10.

Nights of Wednesday  through Friday, September 20 - 22, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Wednesday  through Friday, September 20 - 22, 2017. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Jefferson St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.
  4. Turn left at Monroe St. on-ramp.

Detour for full closure of WB I-10 at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave. 42.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 9/11/17 – 9/15/17

Ramp closures will take place on I-10 at Jefferson Street September 11 - 15. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, September 11 - 15, 2017. 5:00 AM - 5:00 PM

EB on-ramp night:

Monday through Friday, September 11 - 15, 2017. 7:00 PM - 5:00 AM

EB off-ramp night:

Monday through Friday, September 11 - 15, 2017. 7:00 PM - 5:00 AM

WB off-ramp night:

Monday through Friday, September 11 - 15, 2017. 9:00 PM - 6:00 AM

WB on-ramp day:

Monday through Friday, September 11 - 15, 2017. 5:00 AM - 5:00 PM

WB on-ramp night:

Monday through Friday, September 11 - 15, 2017. 9:00 PM - 7:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Ave. 42/Varner Rd. to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street September 11 - 15. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Alternate 1

Night full closure of EB I-10.

Nights of Monday through Friday, September 11 - 15, 2017. 10:00pm - 6:00am

Night alternating lane closure of WB I-10.

Nights of Monday through Friday, September 11 - 15, 2017. 10:00pm - 6:00am

Alternate 2

Night full closure of WB I-10.

Nights of Monday through Friday, September 11 - 15, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Monday through Friday, September 11 - 15, 2017. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Jefferson St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.
  4. Turn left at Monroe St. on-ramp.

Detour for full closure of WB I-10 at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave. 42.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 9/5/17 – 9/8/17

Ramp closures will take place on I-10 at Jefferson Street September 5 - 8. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Tuesday through Friday, September 5 - 8, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Tuesday through Friday, September 5 - 8, 2017. 5:00 AM - 5:00 PM

EB off-ramp night:

Tuesday through Friday, September 5 - 8, 2017. 7:00 PM - 7:00 AM

WB on-ramp day:

Tuesday through Friday, September 5 - 8, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street September 5 - 8. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Alternate 1

Night full closure of EB I-10.

Nights of Tuesday through Friday, September 5 - 8, 2017. 10:00pm - 6:00am

Night alternating lane closure of WB I-10.

Nights of Tuesday through Friday, September 5 - 8, 2017. 10:00pm - 6:00am

Alternate 2

Night full closure of WB I-10.

Nights of Tuesday through Friday, September 5 - 8, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Tuesday through Friday, September 5 - 8, 2017. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Washington St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.
  4. Turn left at Monroe St. on-ramp.

Detour for full closure of WB I-10 at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave. 42.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 8/28/17 – 8/31/17

Lane closures will take place on I-10 at Jefferson Street August 28 - 31. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Alternate 1

Night full closure of EB I-10.

Nights of Monday through Thursday, August 28 - 31, 2017. 10:00pm - 6:00am

Night alternating lane closure of WB I-10.

Nights of Monday through Thursday, August 28 - 31, 2017. 10:00pm - 6:00am

Alternate 2

Night full closure of WB I-10.

Nights of Monday through Thursday, August 28 - 31, 2017. 10:00pm - 6:00am

Night alternating lane closure of EB I-10.

Nights of Monday through Thursday, August 28 - 31, 2017. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Washington St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.
  4. Turn left at Monroe St. on-ramp.

Detour for full closure of WB I-10 at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave. 42.

Continue to Washington St. on-ramp.

 

Ramp closures will take place on I-10 at Jefferson Street August 28 - 31. The purpose of these closures is to  continue bridge and roadway construction activities.

 

Closure Schedule

EB on-ramp day:

Monday through Thursday, August 28 - 31, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Monday through Thursday, August 28 - 31, 2017. 5:00 AM - 5:00 PM

WB on-ramp day:

Monday through Thursday, August 28 - 31, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

Jefferson Interchange Notice of Work, 8/21/17 – 8/25/17 (Updated)

Ramp closures will take place on I-10 at Jefferson Street August 21 - 25. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB off-ramp day:

Thursday and Friday, August 24 - 25, 2017. 5:00 AM - 5:00 PM

WB on-ramp day:

Monday through Friday, August 21 - 25, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street August 21 - 25. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

EB I-10 full closure night:

Monday through Friday, August 21 - 25, 2017. 10:00 PM - 6:00 AM

Detour for full closure of EB I-10 at Jefferson St.

  1. Exit at Washington St. and turn left.
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.

Turn left at Monroe St. on-ramp.

Jefferson Interchange Notice of Work, 8/14/17 – 8/18/17

Ramp closures will take place on I-10 at Jefferson Street August 14 - 18. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, August 14 - 18, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Monday through Friday, August 14 - 18, 2017. 5:00 AM - 5:00 PM

WB on-ramp day:

Monday through Friday, August 14 - 18, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Turn right at Varner Rd.

Continue on Varner Rd. to Washington St. WB I-10 on-ramp.

Jefferson Interchange Notice of Work, 8/11/17

Lane closures will take place on I-10 at Jefferson Street August 11. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

WB I-10 alternating lane closures night:

Friday, August 11, 2017. 10:00 PM - 6:00 AM

WB loop on-ramp day:

Friday, August 11, 2017. 5:00 AM - 5:00 PM

Detour for closure of WB I-10 Loop On-ramp at Jefferson St.

  1. Continue on Indio Blvd. north.
  2. Turn left at Varner Rd.
  3. Continue on Varner Rd. to Washington St. WB on-ramp.

 

Jefferson Interchange WB I-10 Onramp Closure

The existing WB I-10 onramp at Jefferson Street will be permanently closed on August 7, 2017 at 5:00 AM.

The new permanent WB onramp will open on August 14, 2017 at the new location off of the new Jefferson Street Bridge.

During the closure (August 7 - August 14), please use the following detours:

NB Jefferson Street Traffic to WB I-10

Use the new WB Loop Onramp to access the Freeway.

SB Jefferson Street to WB I-10
Use WB Varner Road to the WB onramp at Washington Street.

Jefferson Interchange Notice of Work, 8/7/17 – 8/11/17

Ramp closures will take place on I-10 at Jefferson Street August 7 - 11. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, August 7 - 11, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Monday through Friday, August 7 - 11, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 7/24/17 – 7/28/17

Ramp closures will take place on I-10 at Jefferson Street July 24 - 28. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, July 24 - 28, 2017. 5:00 AM - 5:00 PM

WB on-ramp at Jefferson St. day:

Monday through Friday, July 24 - 28, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Continue on Varner Rd. to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 7/20/17

Ramp closures will take place on I-10 at Jefferson Street July 20. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB off-ramp day:

Thursday, July 20, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 7/17/17 – 7/21/17

Ramp closures will take place on I-10 at Jefferson Street July 17 - 21. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, July 17 - 21, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Jefferson Interchange Ramp Closure, 7/14/17

Ramp closures will take place on I-10 at Jefferson Street July 14. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB off-ramp day:

Friday, July 14, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Updated: Jefferson Interchange Notice of Work, 7/10/17 – 7/14/17

**Update** Closures for Thursday night and Friday night have been cancelled.

Lane closures will take place on I-10 at Jefferson Street July 10 - 14. The purpose of these closures is to demolish the Old Jefferson St. Bridge.

Closure Schedule

Night full closure of EB I-10.

Nights of Monday through Wednesday, July 10 - 12, 2017. 8:00pm - 6:00am

Nights of Thursday through Friday, July 13 - 14, 2017. 9:00pm - 6:00am

Night full closure of WB I-10.

Nights of Monday through Wednesday, July 10 - 12, 2017. 8:00pm - 6:00am

Nights of Thursday through Friday, July 13 - 14, 2017. 9:00pm - 6:00am

Detour for full closure of EB I-10.

  1. Exit at Washington St. and turn left
  2. Turn right at Varner Rd.
  3. Turn right at Monroe St.
  4. Turn left at Monroe St. on-ramp.

Detour for full closure of WB I-10.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave 42.
  3. Continue on Varner Rd. to Washington St. on-ramp.

Note: Traffic will be flagged through the EB and WB I-10 off-ramp and other intersections along the detour route.

Jefferson Interchange Notice of Work, 7/6/17 – 7/7/17

Ramp closures will take place on I-10 at Jefferson Street July 6 - 7. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Thursday through Friday, July 6 - 7, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Thursday through Friday, July 6 - 7, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 7/3/17 – 7/7/17

Ramp closures will take place on I-10 at Jefferson Street July 3 -7. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, July 3 - 7, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Monday through Friday, July 3 - 7, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 6/29/17

On the afternoon of Thursday, June 29, 2017, the new eastbound off-ramp and eastbound loop on-ramp will be opened to traffic. The opening of these ramps will allow for the demolition of the old Jefferson St. bridge on July 10, 2017.

Note: There will be a new signal at the intersection of Jefferson St. and the new ramps.

Jefferson Interchange Notice of Work, 6/26/17 – 6/29/17

Ramp closures will take place on I-10 at Jefferson Street June 26 - 30. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, June 26 - 30, 2017. 5:00 AM - 5:00 PM

EB off-ramp day:

Monday through Friday, June 26 - 30, 2017. 5:00 AM - 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

Lane closures will take place on I-10 at Jefferson Street June 26 - 28. The purpose of this closure is for the removal of k-rail from the new EB aux lane and to stripe the new EB onramp tie in to mainline.

Night alternating lane closure of EB I-10.

Nights of Monday to Wednesday, June 26 - 28, 2017. 10:00pm - 6:00am