CVWD Storm Channel Project Updates

Current CVWD Storm Channel Project Updates

  • Pond 1 had been drained and demolished.
  • All existing sidewalk in the construction zone has been demolished.
  • The reeds and pond liner has been removed.
  • The contractor, Sukut, is waiting for the soil to dry out presumably before they start the major excavation.

North Channel Pond 2 Conversion Project

  • Project will commence on March 7, with a completion time frame of 42 days.
  • Area will be fenced off from the south end of the Jefferson underpass entrance and along the pony-walls of the surrounding homes.
  • Landscape Unlimited will be delivering their equipment needed to drain and demolished the pond on Monday, March 7.
  • All wildlife such as turtles and fishes will be relocated to Pond 3.