The following closures are scheduled to take place on I-10 at the Jefferson Street Interchange between May 11 and May 22, 2015.

 CLOSURE 1

DAY-TIME CLOSURE: EB I-10 on-ramp at Jefferson Street

Date/Time

Monday, May 11 to Friday, May 15, 2015
6:00 AM to 5:00 PM

 Purpose

To allow construction crews to perform earth moving operations

 Detour 

  1. From Jefferson Street, go east on Varner Road.
  2. Turn right at Monroe Street.
  3. Turn left at the EB I-10 on-ramp.

 

CLOSURE 2
NIGHT-TIME CLOSURE: WB I-10 on-ramp at Jefferson Street

Date/Time

Night of Wednesday, May 13, 2015
10:00 PM to 6:00 AM

Purpose
To allow construction crews to place k-rail

Detour

  1. From Jefferson Street, go west on Varner Road.
  2. Turn left onto the WB I-10 on-ramp at Washington Street.

 

CLOSURE 3
NIGHT-TIME CLOSURE: WB I-10 off-ramp at Jefferson Street

Date/Time
Nights of Wednesday, May 13 and Thursday, May 14, 2015
10:00 PM to 6:00 AM

Purpose
To allow construction crews to place k-rail

Detour

  1. Continue west on I-10 and exit at the Washington St.on-ramp.
  2. Turn right at Varner Rd.

 

CLOSURE 4
NIGHT-TIME CLOSURE: WB I-10 number 2 and 3 lanes at the Jefferson Street off-ramp

Date/Time
Nights of Wednesday, May 13 and Thursday, May 14, 2015
10:00 PM to 6:00 AM

Purpose
To allow construction crews to place k-rail and switch traffic to the new temporary WB I-10 off-ramp

Detour
No detour is necessary.

CLOSURE 5
DAY-TIME CLOSURE: EB I-10 on-ramp at Jefferson Street 

Date/Time
Monday, May 18 to Friday, May 22, 2015
6:00 AM to 5:00 PM

Purpose
To allow construction crews to perform earth moving operations

Detour

  1. From Jefferson Street, go east on Varner Road.
  2. Turn right at Monroe Street.
  3. Turn left at the EB I-10 on-ramp.