Ramp closures will take place on I-10 at Jefferson Street October 10 - 14. The purpose of these closures is to continue bridge and roadway construction activities.
Closure Schedule
EB on-ramp day: Tuesday through Friday, October 11 - 14, 2016 6:00 AM - 4:00 PM
EB off-ramp night: Monday through Wednesday, October 10 - 12, 2016 7:00 PM - 4:00 PM (21 hour closure)
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour for closure of EB I-10 On-ramp at Jefferson St.
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
- Turn left at the EB I-10 on-ramp.
Detour for closure of EB I-10 Off-ramp at Jefferson St.
- Go east on I-10 exit at Monroe St.
- Turn left at Monroe St.
- Turn left at Ave. 42/Varner Rd. back to Jefferson St.