Jefferson Interchange Notice of Work, 11/21/16 – 11/23/16

** This closure has been cancelled **

Ramp closures will take place on I-10 at Jefferson Street November 21 - 23. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day: Monday through Wednesday, November 21 - 23, 2016 5:00 AM - 4:00 PM

EB off-ramp Night: Monday through Tuesday, November 21 - 22, 2016 9:00 PM - 6:00 AM

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

Lane closures will take place on I-10 at Jefferson Street November 21 - 22. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night alternating lane closure of EB I-10.

Night of Monday and Tuesday, November 21 - 22, 2016. 10:00pm - 6:00am

Night alternating lane closure of WB I-10.

Night of Monday and Tuesday, November 21 - 22, 2016. 10:00pm - 6:00am