Jefferson Interchange Notice of Work, 1/3/17 – 1/6/17

Ramp closures will take place on I-10 at Jefferson Street January 3 - 6. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day: Tuesday through Friday, January 3 - 6, 2017. 5:00 AM - 4:00 PM

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

 

Lane closures will take place on I-10 at Jefferson Street January 5 - 6. The purpose of these closures is to continue bridge and roadway construction activities.

Closure Schedule

Night full closure of WB I-10.

Nights of Thursday and Friday, January 5 - 6, 2017. 10:00pm - 6:00am

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on Jefferson St.
  4. Right on Jefferson St. WB on-ramp

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.