Ramp closures will take place on I-10 at Jefferson Street February 1 - 5. The purpose of these closures is to allow the removal of bridge form panels.
Closure Schedule
Date: Monday to Friday. February 1 - 5, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp.
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
Turn left at the EB I-10 on-ramp