Ramp closures will take place on I-10 at Jefferson Street February 29 - March 4. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.
Closure Schedule
Date: Monday to Friday. February 29 - March 4, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour for closure of EB I-10 On-ramp at Jefferson St.
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
Turn left at the EB I-10 on-ramp.