Ramp closures will take place on I-10 at Jefferson Street March 6 - 10. The purpose of these closures is to continue bridge and roadway construction activities.
Closure Schedule
EB on-ramp day:
Monday through Friday, March 6 - 10, 2017. 5:00 AM - 5:00 PM
EB off-ramp day:
Monday through Friday, March 6 - 10, 2017. 5:00 AM - 5:00 PM
WB on-ramp day:
Monday through Friday, March 6 - 10, 2017. 5:00 AM - 5:00 PM
WB off-ramp day:
Monday through Friday, March 6 - 10, 2017. 5:00 AM - 5:00 PM
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour for closure of EB I-10 On-ramp at Jefferson St.
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
- Turn left at the EB I-10 on-ramp.
Detour for closure of EB I-10 Off-ramp at Jefferson St.
- Go east on I-10 exit at Monroe St.
- Turn left at Monroe St.
- Turn left at Ave. 42/Varner Rd. back to Jefferson St.
Detour for closure of WB I-10 On-ramp at Jefferson St.
- Continue on Varner Rd. to Washington St. on-ramp.
Detour for closure of WB I-10 Off-ramp at Jefferson St.
- Exit at Monroe St. and turn right.
- Turn left at Varner Rd./Ave. 42.