Jefferson Interchange Notice of Work, 9/14/15 – 9/18/15

Lane closures will take place on I-10 at Jefferson Street September 14 to 18. The purpose of this closure is to allow construction crews to remove shoring and install backfill in the median. Abutment 1 left side will also be poured during this closure.

Closure Schedule

Date: Nights of Monday through Friday. September 14 - 18, 2015
Time: 8:00 PM - 7:00 AM
Closures: Full Closure of  EB I-10 on-ramp.

Date: Nights of Monday through Friday. September 14 - 18, 2015
Time: 10:00 PM - 6:00 AM
Closures: Closures on EB and WB I-10 will limit traffic to one lane in each direction.

Detour for full closure of EB I-10 on-ramp at Jefferson Street Interchange

  1. From Jefferson Street, go east on Varner Road.
  2. Turn right at Monroe Street.

Turn left at the EB I-10 on-ramp.