Phase I Asphalt Repairs Project

JOBSITE: Phase I – Avenida San Ignacio, Corte San Carlos, Corte Santa Susana, Corte Los Bancos, Calle Santa Anita, Avenida Manzanillo, Calle Santa Monica, Corte Santa Carmela, Calle Santa Paula

CONCRETE REPAIRS

4/8 – Friday - No Parking & Driving on Concrete Areas

ASPHALT REPAIRS

Yellow Section

4/12 – Tuesday – Mill Streets – No Parking on Streets
4/14 – Thursday – No Parking & Driving on Streets

Blue Section

4/13 – Wednesday – No Parking on Streets
4/15 – Friday – No Parking & Driving on Streets

VALVE ADJUSTMENT

4/18 thru 4/20 – No Parking & Driving on Concrete Areas

PLEASE OBSERVE THE FOLLOWING ITEMS:

On concrete repairs day and while concrete is curing, access will be limited around concrete areas. Do not drive over concrete until after asphalt work has been completed.

Tuesday 4/12 and Wednesday 4/13

  • Cars will be able to come and go as they please
  • Residents and Guest may only parking on their driveway
  • ALL ROADWAYS AND PARKING AREAS MUST BE CLEAR (per diagram)

Thursday 4/14 and Friday 4/15

  • Residents who reside on street being paved and plan on using their vehicle, please move your car out by 7:00 A.M. and then you may return after 6:00 P.M.
  • There will be no parking or driving on streets
  • ALL ROADWAYS AND PARKING AREAS MUST BE CLEAR (per diagram)

Mon 4/18 – Wed 4/20

  • Cars will be able to come and go as they please, only parking in their driveway is permitted

During this process we would ask you to please adhere to the following precautionary measures:

  • Please proceed slowly throughout this general area.
  • Please be mindful of road surface conditions (dust, etc.)
  • Please be mindful of trucks and equipment.
  • Anticipate minimal traffic delays.

PLEASE NOTE: THIS SCHEDULE IS BASED ON WEATHER PERMITTING

These instructions are being provided to prevent any damages to your vehicle(s) or personal property. Therefore, it is extremely necessary that you take responsibility to follow them.