Project Updates (December 16)

Phase II Ground-cover Restoration Project

The Phase II ground-cover restoration project began on Monday, December 9. The project is expected to last between 8 to 10 weeks. Worksite safety signs are posted on each end of the street. Please take extra caution for equipment and dump trucks while driving and walking around the worksite.

 

Phase III Mailbox Stucco Columns Restoration

The Phase III mailboxes stucco columns restoration project began on Tuesday, December 10. The project is scheduled to be completed by Friday, December 20. The contractor will be repairing any stucco damages and repainting the columns with two coats of paint.

 

 

Montecito North Landscape Enhancement Project

The Montecito north landscape enhancement project began on Tuesday, December 10. The project is scheduled to be completed by Tuesday, December 24. The project consists of new ground-cover gravel and plants that will significantly enhance the view of the landscape from inside and outside the Montecito Clubhouse.