Ramp closures will take place on I-10 at Jefferson Street March 20 - 24. The purpose of these closures is to continue bridge and roadway construction activities.
Closure Schedule
EB on-ramp day:
Monday through Friday, March 20 - 24 2017. 5:00 AM - 5:00 PM
EB on-ramp night:
Nights of Wednesday through Friday, March 22 - 24, 2017. 9:00 PM - 6:00 AM
EB off-ramp night:
Nights of Wednesday through Friday, March 22 - 24, 2017. 9:00 PM - 6:00 AM
Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.
Detour for closure of EB I-10 On-ramp at Jefferson St.
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
- Turn left at the EB I-10 on-ramp.
Detour for closure of EB I-10 Off-ramp at Jefferson St.
- Go east on I-10 exit at Monroe St.
- Turn left at Monroe St.
Turn left at Ave. 42/Varner Rd. back to Jefferson St.
Lane closures will take place on I-10 at Jefferson Street March 22 - 24. The purpose of these closures is to continue bridge and roadway construction activities.
Closure Schedule
Night full closure of EB I-10.
Nights of Wednesday through Friday, March 22 - 24, 2017. 10:00pm - 6:00am
Night alternating lane closure of EB I-10.
Nights of Wednesday through Friday, March 22 - 24, 2017. 10:00pm - 6:00am
Detour for full closure of EB I-10.
- Take the EB I-10 off-ramp at Jefferson St.
- Left on existing Jefferson over-crossing
- Right on Varner Rd.
- Right on Monroe St.
- Left on EB I-10 on-ramp at Monroe St.
Note: Traffic will be flagged through the EB I-10 off-ramp and other intersections along the detour route.