Montecito Outdoor Pool Deck Replacement Project Update

The contractor has completed the installation of the new pool deck underground drain system and concrete deck. The newly installed concrete is currently in the curing process and is expected to be fully cured by the week of November 20. The contractor is estimated to begin the installation of the Kool Deck overlay on Monday, November 20. The installation will require two weeks to complete. The Montecito Outdoor Pool is projected to reopen on Monday, December 4. Any updates to this timeline will be provided via on-site notices and notifications on the SCSH website.

We appreciate and thank you for your patience throughout this process.

For any questions or concerns, please contact the Facilities Maintenance Department at 760-345-4349 ext. 2401.