Jefferson Interchange Notice of Work, 4/26/16

Due to high winds last night, this work has been moved to Tuesday April 26.

Ramp closures will take place on I-10 at Jefferson Street April 26. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

WB on-ramp night:

Tuesday, April 26, 2016 7:00 PM - 9:00 AM

WB off-ramp night: 

Tuesday, April 26, 2016 7:00 PM - 10:00 PM

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Continue on Varner Rd. to Washington St. on-ramp.

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right.

Turn left at Varner Rd./Ave. 42.

Jefferson Interchange Notice of Work, 4/25/16 – 4/26/16

Lane closures will take place on I-10 at Jefferson Street April 25 - 26. The purpose of these closures is to continue bridge construction activities.

Closure Schedule

Alternate 1

Night closure of EB I-10. Closure of alternating lanes on WB 1-10.

Nights of Monday to Tuesday, April 25 - 26, 2016. 10:00pm - 6:00am

Alternate 2

Night closure of WB I-10. Closure of alternating lanes on EB 1-10.

Night of Tuesday, April 26, 2016. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10.

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing
  3. Right on Varner Rd.
  4. Right on Monroe St.
  5. Left on EB I-10 on-ramp at Monroe St.

Note: Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Left on Jefferson St.
  4. Right on Jefferson St. WB on-ramp

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

 

Ramp closures will take place on I-10 at Jefferson Street April 25 - 26. The purpose of these closures is to  continue bridge construction activities.

Closure Schedule

EB on-ramp day:

Monday through Thursday, April 25 - 28, 2016 6:00 AM - 4:00 PM

EB on-ramp night:

Monday through Tuesday, April 25 - 26, 2016 7:00 PM - 9:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

Jefferson Interchange Notice of Work, 4/18/16 – 4/19/16

Lane closures will take place on I-10 at Jefferson Street April 18 - 19. The purpose of these closures is to continue bridge construction activities.

Closure Schedule

Night closure of EB I-10. Closure of alternating lanes on WB I-10.

Nights of Monday to Tuesday, April 18 - 19, 2016. 10:00pm - 6:00am

Detour for full closure of EB I-10.

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing
  3. Right on Varner Rd.
  4. Right on Monroe St.
  5. Left on EB I-10 on-ramp at Monroe St.

Note: Traffic will be flagged through the EB I-10 off-ramp.

Ramp closures will take place on I-10 at Jefferson Street April 18 - 22. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, April 18 - 22, 2016 6:00 AM - 4:00 PM

EB on-ramp night:

Monday through Tuesday, April 18 - 19, 2016 7:00 PM - 9:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

IPD Coachella Press Release

Sergeant Daniel Marshall from Indio Police Department

Hi Neighbors,

In case you missed it here is the traffic press release for Coachella:

2016 Coachella Valley Music and Arts Festival

Weekend 1 and Weekend 2 Traffic Information

Indio, California – April 6, 2016 – The Coachella Valley Music and Arts Festival will be held at the Empire Polo Club on April 15, 16 and 17 and April 22, 23 and 24, 2016, at 81-800 Avenue 51.

ON FRIDAY APRIL 15 THROUGH SUNDAY APRIL 17 AND FRIDAY APRIL 22 THROUGH SUNDAY APRIL 24, THE FOLLOWING ROADWAYS WILL BE PRIMARY ACCESS ROUTES FOR THE FESTIVALS:

  • Jefferson Street, southbound, from I-10 to Avenue 52
  • Washington Street, southbound, from I-10 to Avenue 52
  • Monroe Street, southbound, from I-10 to Avenue 52
  • Highway 111 at Jefferson Street
  • Highway 111 at Monroe Street
  • I-10 exit eastbound at Jefferson
  • I-10 exit eastbound at Monroe

ROAD CLOSURES:

  • Avenue 49 between Hjorth Street and Monroe Street
  • Avenue 50 between Madison Street and Jackson Street
  • Hjorth Street between Avenue 49 and Avenue 50
  • Madison Street between Avenue 49 and Avenue 52

ALTERNATE ROUTES:

  • North and South travel, use Washington Street, Jackson Street, Calhoun Street and Golf Center Parkway
  • East and West travel, use Fred Waring Drive, Miles Avenue, Avenue 48 and Avenue 54.

UBER/TAXI LOCATION:

  • Avenue 49 and Monroe Street on the southwest corner inside the venue.

PARENT DROP OFF AND PICK UP:

  • Avenue 52 and Madison Street inside the venue

Continued FOR 2016: Absolutely NO PEDESTRIANS OR PEDESTRIAN FESTIVAL ACCESS will be allowed on Monroe Street between Avenue 49 and Avenue 52. Pedestrian Access IS available at the corner of Avenue 49 & Monroe Street AND at the corner of Avenue 52 & Madison Street.

Please note that golf carts are not permitted on any of the above-listed streets.

There will be approximately 35,000 guests shuttled into and out of the concert venue from various locations throughout the Coachella Valley to help ease traffic conditions.

For concert questions or problems, please call 760-391-4112 or email to concertinfo@indio.org

Jefferson Interchange Notice of Work, 4/11/16 – 4/15/16

Ramp closures will take place on I-10 at Jefferson Street April 11 - 15. The purpose of these closures is to  continue bridge construction activities.

Closure Schedule

EB on-ramp day:  Monday through Friday, April 11 - 15, 2016 6:00 AM - 4:00 PM

EB on-ramp night:  Monday through Friday, April 11 - 15, 2016 9:00 PM - 9:00 AM

EB off-ramp day:  Monday through Wednesday, April 11 - 13, 2016 6:00 AM - 4:00 PM

EB off-ramp night:  Monday through Wednesday, April 11 - 13, 2016 9:00 PM - 9:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Jefferson Interchange Notice of Work, 4/3/16 – 4/8/16 – Updated

Update 4/5: All night closures cancelled for this week.

Lane closures will take place on I-10 at Jefferson Street April 3 - 8. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

Alternate 1

Night closure of EB I-10. Full closure of EB I-10.

Night of Monday to Friday, April 4 - 8, 2016. 10:00pm - 6:00am

Alternate 2

Night closure of WB I-10. Full closure of WB I-10.

Night of Sunday to Friday, April 3 - 8, 2016. 10:00pm - 6:00am

Alternate 3

Night closure of EB I-10. Closure of alternating lanes on EB 1-10.

Night of Monday to Friday, April 4 - 8, 2016. 10:00pm - 6:00am

Alternate 4

Night closure of WB I-10. Closure of alternating lanes on WB 1-10.

Night of Monday to Friday, April 4 - 8, 2016. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Detour for full closure of EB I-10.

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing
  3. Right on Varner Rd.
  4. Right on Monroe St.
  5. Left on EB I-10 on-ramp at Monroe St.

Note: Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10.

  •  Take the temporary WB I-10 off-ramp at Jefferson St.
  • Left on Varner Rd.
  • Left on Jefferson St.
  • Right on Jefferson St. WB on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

 

Ramp closures will take place on I-10 at Jefferson Street April 3 - 8. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

EB on-ramp and off-ramp day:

Monday through Friday, April 4 - 8, 2016 6:00 AM - 4:00 PM

EB on-ramp and off-ramp night:

Monday through Friday, April 4 - 8, 2016 9:00 PM - 9:00 AM

WB on-ramp night:

Sunday through Friday, April 3 - 8, 2016 9:00 PM - 9:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Amateur Radio Training (RACES)

The Riverside County Radio Amateur Civil Emergency Services (RACES) and city of Indio are hosting amateur radio training.

What: Amateur Radio, Technician Level
When: April 16, 2016 and April 23, 2016 from 8 am to 4 pm
Where: City of Indio Emergency Operations Center, 45222 Towne Street, Indio 92201
Cost: Book plus licensing fees (apx. $30)

To register, please e-mail Michelle Caldwell at michelle.caldwell@fire.ca.gov. Please provide your name, contact number, and advise if you need to purchase the course book.

Seating is limited. Register today!

Jefferson Interchange Notice of Work, 3/28/16 – 3/29/16

Lane closures will take place on I-10 at Jefferson Street March 28 - 29. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.
Closure Schedule

Alternate 1

Night closure of EB I-10. Closure of alternating lanes on EB 1-10.

Nights of Monday to Tuesday, March 28 - 29, 2016. 10:00pm - 6:00am

Alternate 2

Night closure of WB I-10. Closure of alternating lanes on WB 1-10.

Nights of Monday to Tuesday, March 28 - 29, 2016. 10:00pm - 6:00am

Note: Only one alternative will be used each night.

Jefferson Interchange Notice of Work, 3/21/16 – 3/24/16

Ramp closures will take place on I-10 at Jefferson Street March 21 - 24. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

EB on-ramp and off-ramp day: Monday through Thursday, March 21 - 24, 2016 6:00 AM - 4:00 PM

EB on-ramp and off-ramp night: Monday through Thursday, March 21 - 24, 2016 9:00 PM - 9:00 AM

WB on-ramp and off-ramp day: Monday through Thursday, March 21 - 24, 2016 6:00 AM - 4:00 PM

WB on-ramp and off-ramp night: Monday through Thursday, March 21 - 24, 2016 9:00 PM - 9:00 AM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

Detour for closure of WB I-10 On-ramp at Jefferson St.

  1. Continue on Varner Rd. to Washington St. on-ramp

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St.

Turn left at Varner Rd./Ave. 42

Jefferson Interchange Notice of Work, 3/14/16 – 3/18/16

Ramp closures will take place on I-10 at Jefferson Street March 14 - 18. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

EB on-ramp and off-ramp day: Monday through Friday, March 14 - 18, 2016 6:00 AM - 4:00 PM

EB on-ramp and off-ramp night: Monday through Friday, March 14 - 18, 2016 9:00 PM - 6:00 AM

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.

Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

Lane closures will take place on I-10 at Jefferson Street March 14 - 18. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Night closure of EB I-10. Full closure of EB I-10.

Night of Wednesday, March 16, 2016. 10:00pm - 6:00am

Night closure of WB I-10. Full closure of WB I-10.

Night of Thursday, March 17, 2016. 10:00pm - 6:00am

Night closure of EB I-10. Closure of alternating lanes on EB 1-10.

Nights of Monday to Friday, March 14 - 18, 2016. 10:00pm - 6:00am

Night closure of WB I-10. Closure of alternating lanes on WB 1-10.

Nights of Monday to Friday, March 14 - 18, 2016. 10:00pm - 6:00am

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for full closure of EB I-10.

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing
  3. Right on Varner Rd.
  4. Right on Monroe St.
  5. Left on EB I-10 on-ramp at Monroe St.

Note: Traffic will be flagged through the EB I-10 off-ramp.

Detour for full closure of WB I-10.

    1. Take the temporary WB I-10 off-ramp at Jefferson St.
    2. Left on Varner Rd.
    3. Left on Jefferson St.
    4. Right on Jefferson St. WB on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Jefferson Interchange Notice of Work, 3/7/16 – 3/11/16

Lane closures will take place on I-10 at Jefferson Street March 7 - 11. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Alternate 1

Night closure of EB I-10. Closure of alternating lanes on EB 1-10.

Nights of Monday through Friday. March 7 - 11, 2015  10:00 PM - 6:00 AM

Alternate 2

Night closure of EB I-10. Full closure of EB I-10.

Nights of Monday through Friday. March 7 - 11, 2015  10:00 PM - 6:00 AM

Note: Alternate 1 and Alternate 2 will never be implemented simultaneously.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for Alternate 2

  1. Take the EB I-10 off-ramp at Jefferson St.
  2. Left on existing Jefferson over-crossing
  3. Right on Varner Rd.
  4. Right on Monroe St.
  5. Left on EB I-10 on-ramp at Monroe St.

Note: Traffic will be flagged through the EB I-10 off-ramp.

City of Indio to Kick Off Town Hall Series on Thursday, March 3

The City of Indio will host the first in a series of Town Hall meetings on Thursday, March 3 at 5:30 pm in the Heritage Room at Heritage Palms Country Club in Indio. Mayor Glenn Miller and members of the City Council will be on hand to answer questions about city programs, developments, special events, service priorities and infrastructure needs. Residents, business owners and other interested parties are encouraged to attend this free event.

The purpose of the Town Hall series is to provide a forum for locals to take an active role in city government. The City Council will receive input from residents while considering their concerns, requests, suggestions, observations and questions.

“As a city, It’s important for us to be able to engage our residents, hear their questions and concerns, and respond appropriately,” Miller said. “The Town Hall format is a great venue to interact, share news and make announcements. It’s about complete transparency and starting a conversation with the community.”

Heritage Palms Country Club is located at 44291 S. Heritage Palms Drive, Indio.

The next Town Hall meeting is slated for March 10 in the Palm Terrace Hall at Indian Palms Country Club, 48630 Monroe Street, Indio.

Indio CERT Training: April 8, 9, and 10

Community Emergency Response Team (CERT) Training

CERT training institutes a practical approach to handling emergency and disaster situations. CERT promotes readiness, self-sufficiency, teamwork, rescuer safety and doing the greatest good for the greatest number of people. Students learn how to organize themselves during a disaster, manage utilities, extinguish small fires, search for and rescue survivors and provide basic disaster medical care.

CERT training will be delivered over the course of three days. Only those who complete all training hours, including practical skills practice, will receive a certificate of completion and free CERT kit.

WHEN:
April 8, 2016 - 5:00 pm – 9:00 pm
April 9, 2016 - 8:00 am – 5:00 pm
April 10, 2016 - 8:00 am – 5:00 pm

WHERE:
City of Indio Emergency Operations Center
45222 Towne Street, Indio

Open to all persons 18 years of age and older

HOW TO REGISTER: Visit rivcocert.org or call 951-955-4700

The City of Indio is committed to ensuring that its programs are fully accessible to and usable by persons with access and functional needs. Those requiring reasonable accommodations should call 760-766-5802 or e-mail indiocert@indio.org.

Class size is limited. Register today! It’s FREE!!

Jefferson Interchange Notice of Work, 3/1/16 – 3/3/16

Lane closures will take place on I-10 at Jefferson Street March 1 - 3. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Night of Tuesday to Thursday, March 1 - 3, 2016.
Time: 10:00 PM - 6:00 AM

Closures:

Alternating lane closures EB I-10 Freeway

Jefferson Interchange Notice of Work, 2/29/16 – 3/4/16

Ramp closures will take place on I-10 at Jefferson Street February 29 - March 4. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

Date: Monday to Friday. February 29 - March 4, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

Jefferson Interchange Update

The realigned I-10 WB on-ramp was opened on Friday afternoon. This realignment provides an extended auxiliary lane to facilitate smooth merges onto the I-10 freeway.

Traffic speed limits in both directions have been reduced on the I-10 through the Jefferson St. construction zone to 55 mph.  CHP will be enforcing this speed limit at all times until the completion of the project.

Jefferson Interchange Notice of Work, 2/22/16 – 2/26/16

Ramp closures will take place on I-10 at Jefferson Street February 22 - 26. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations and to continue bridge construction activities.

Closure Schedule

Date: Wednesday to Friday. February 17 - 19, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Jefferson Interchange Notice of Work, 2/17/16 – 2/19/16

Ramp closures will take place on I-10 at Jefferson Street February 17 - 19. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Wednesday to Friday. February 17 - 19, 2016
Time: 6:00 AM - 4:00 PM
Closures: Full closure of EB on-ramp at Jefferson St.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp.

 

Night closures will take place on WB I-10 at Jefferson Street February 17 - 19. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Full closure of WB I-10 on-ramp:

Thursday, February 18 6:00am to Friday, February 19, 2016 6:00am

Alternate 1

Closure of 2 and 3 lanes on WB I-10.

Wednesday through Friday, February 17 - 19, 2016 10:00pm - 6:00am

Alternate 2

Full closure of WB I-10.

Thursday through Friday, February 18 - 19, 2016 10:00pm - 6:00am

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Continue to Washington St. on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue to Washington St. on-ramp.

Jefferson Interchange Notice of Work, 2/8/16 – 2/11/16

Ramp closures will take place on I-10 at Jefferson Street February 8 - 11. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Date: Monday to Thursday. February 8 - 11 2016

Time: 6:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp and off-ramp.

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

Detour for closure of EB I-10 Off-ramp at Jefferson St.

  1. Go east on I-10 and exit at Monroe St.
  2. Turn left at Monroe St.
  3. Turn left at Ave. 42/Varner Rd. back to Jefferson St.

 

This work has been cancelled for this week:

Night closures will take place on WB I-10 at Jefferson Street February 8 - 11. The purpose of these closures is to allow placement of new roadway pavement at the new on/off ramp locations.

Closure Schedule

Closure of 2 and 3 lanes on WB I-10: Monday through Wednesday, February 8 - 10, 2016 10:00pm - 6:00am

Full closure of WB I-10 on-ramp: Monday through Thursday, February 8 - 11, 2016 9:00pm - 7:00am

Full closure of WB I-10: Thursday, February 11, 2016 10pm - 6:00am

Detour for full closure of WB I-10.

  1. Take the temporary WB I-10 off-ramp at Jefferson St.
  2. Left on Varner Rd.
  3. Continue to Washington St. on-ramp.

Note: Traffic will be flagged through the temporary WB I-10 off-ramp/Varner Rd. intersection.

Detour for closure of WB I-10 On-ramp at Jefferson St.

Continue to Washington St. on-ramp.

Law School Opens in Indio – First In the Coachella Valley

City of Indio celebrated the official opening of the first law college in our Valley.

John P. Dolan and his wife, Irene Dolan started this law school which focuses on educating lawyers on the skills of court room litigation.

The new school has replicas of a Federal court, Superior Court and Appellate Court to help train each student how to work in each of the different court rooms.

Officials showed up to congratulate John and Irene; Senator Jeff Stone, Assemblyman Eduardo Garcia, District Attorney Mike Hestrin, Indio City Mayor Glenn Miller with Mayor Pro-tem Elaine Holmes and Council member Troy Strange, Supervisor John Benoit and Indio Police Chief Richard Twiss.

SKYWARN Training to be held in the City of Indio

The National Weather Service will provide SKYWARN training at the City of Indio Emergency Operations Center, located at 45222 Towne Street, Indio on February 12, 2016, from 10 am to 11:30 am

For additional information about the SKYWARN program, please visit: http://skywarn.org/about/

To register for the upcoming training, please e-mail michelle.caldwell@fire.ca.gov.

Best regards,

Michelle Caldwell
Emergency Services Coordinator
County of Riverside
Emergency Management Department
In Cooperation with the City of Indio

Jefferson Interchange Notice of Work, 2/4/16

Lane closures will take place on I-10 at Jefferson Street February 4. The purpose of this closure is to allow construction crews to place concrete pavement on the new EB on ramp.

Closure Schedule

Date: Night of Thursday, February 4, 2016.
Time: 10:00 PM - 6:00 AM

Closures:

Closure of 2 and 3 lanes on EB 1-10.

Jefferson Interchange Notice of Work, 2/1/16 – 2/5/16

Ramp closures will take place on I-10 at Jefferson Street February 1 - 5. The purpose of these closures is to allow the removal of bridge form panels.

Closure Schedule

Date: Monday to Friday. February 1 - 5, 2016

Time: 6:00 AM - 4:00 PM

Closures: Full closure of EB on-ramp.

Note: Friday closures will not be implemented except as a contingency to complete work delayed by weather events to keep the project on schedule.

Detour

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.

Turn left at the EB I-10 on-ramp